Construction Start: Pulp & Paper - JELF OCT 2022, Von Sperber
Please be advised that FMAS Operations, Southeast Sector, will carry out the following project:Â 22-029 PULP & PAPER - JELF OCT 2022, Von Sperber
¶Ù±ð²õ³¦°ù¾±±è³Ù¾±´Ç²Ô:ÌýTo carry out electrical works between Lab 202 and existing electrical panel in 2-Hall1
Construction start date:Â November 4, 2024.
Planned construction end date:Â November 30, 2024
Work schedule:Â Monday to Friday, 6 a.m. to 3 p.m., on a part-time basis
Project Manager and Assistant Project Manager: mona.modarressi [at] mcgill.ca (Mona Moudarressi) /Ìýrabih.farah [at] mcgill.ca (Rabih Farah)
Contact for building users:
Building Director – Chemistry: jean-marc.gauthier [at] mcgill.ca (Jean-Marc Gauthier)
--------------------------------------------------------------------------------------------------------
Scope of work:
The work consists
- Installing new outlets in Lab 202
- Installing new breakers in existing panel in 2-Hall1
- Running conduits and cables between the new outlets and the existing panel
- Performing an electrical shutdown (date to be communicated once determined)
Impact & mitigation:
- Protection of the equipment, where needed, in the work zone
- To be coordinated with the lab users and building administration
- Works during the day on a part-time basis
- To be coordinated with the lab users and building administration
- Electrical shutdown:
- To be coordinated with the lab users and building administration
- Impacted staff will be informed in advance
Safety considerations:
Some drilling into materials containing silica is required to fix the new installations to the ceiling. Applicable safety protocols will be put in place, including dust-containment measures such as the use of specialized vacuuming equipment.